STUDIES FOR DEVELOPMENT OF PORTS AT JAIGAD, AGARGULE,VIJAYDURG AND REDI
Project Code : CNP 0823
Project Title : Studies for development of ports at Jaigad, Agargule, Vijaydurg and Redi
Key words : Breakwater, Refraction, Waves
Area of Research : CZM
Category : CNP
Status : Ongoing
Sponsoring Agency :
The Commisioner, Water Transport, MumbaiCollaborating Agencies :
Date of Commencement : November 1996
Date of Completion ; October 1997
Estimated Total Cost : ( RS. in lakhs ) : 22 Lakhs
Project Leader : Shri N. M. Anand
Project Team :
Objectives/ Scope of the Project : Evalution of design parameters based on the available data for hydaulic model study of Breakwater Sections and Breakwater Heads
Present Status : Ongoing
Work Plan with Phases/ Milestones: Project will be completed October 1997
Expected S & T Output :